From our plans’ materials lists, at prices on 2026-11-15, a timber zome’s shell materials cost about $33 per square foot of floor: $5,100 for a 16-foot pod, $14,600 for a 25-foot cabin, $37,400 for a 40-foot home. With base wall, floor, entry and fasteners: $14,800, $29,500 and $60,000. A contractor-built home costs several times its shell.
Below is how we got those numbers, line by line, and how to bracket the parts our plans don’t cover. Everything is priced from the same three plans: the Mira Zome 16 glamping pod (155 sq ft), the Capella Zome 25 cabin (430 sq ft) and the Borealis Zome 40 home (1,120 sq ft), all in their standard 2x6 editions.
Three ways to pay for a zome
| Route | What you pay for | Capella Zome 25 (430 sq ft), our estimate |
|---|---|---|
| DIY shell and base | Materials only, your own labor | about $29,500 in plan materials |
| Owner-builder with trades | Plan materials, plus hired plumbing, electrical, HVAC and interiors | about $67,500, plus your time |
| Turnkey | A contractor builds everything | about $85,000 before shell labor, so likely $200+ per sq ft |
The rest of this page explains each line.
How we priced it
Quantities come from each plan’s build guide: the lumber packed into stock lengths, sheet counts with waste, roofing squares, glazing area, foam board feet, fasteners and connectors. They’re the numbers a builder takes to the yard.
Prices are web prices for single pieces at McCoy’s Building Supply, San Marcos, Texas, read on 2026-11-15. McCoy’s is a regional building-supply chain rather than a national big box; national big-box web prices weren’t available to our price check that day, so treat these as one Southern data point. Some specifics:
| Item | Price used |
|---|---|
| 2x6 x 12’, Southern Pine No. 2 | $8.99 |
| 2x6 x 16’, Southern Pine No. 2 | $12.89 |
| 2x10 x 12’, Southern Pine No. 2 | $16.39 |
| 6x6 x 12’, ground-contact treated | $58.99 |
| 15/32” CDX plywood, 4’ x 8’ | $27.19 |
| 23/32” T&G plywood subfloor, 4’ x 8’ | $51.29 |
| Architectural shingles, per bundle (3 per square) | $44.99 |
| Synthetic underlayment, 286’ x 42” roll | $90.99 |
| Two-part spray foam kit, about 650 board feet | $1,157.49 (about $1.78 per board foot) |
| 36” x 80” steel prehung exterior door | $236.99 |
| 3 1/2” structural screws, 50-pack | $37.99 |
| 80-lb bag of concrete mix | $5.99 |
Where a length wasn’t listed (a 14- or 16-foot 2x10, for example), we priced it at the per-foot rate of the nearest listed length. For context, lumber futures stood at $520 per thousand board feet on 2026-11-13, 7.2% below a year earlier (Trading Economics). Retail prices also vary a lot by region and species: the same store asked $17.99 for a 16-foot Western-species 2x6, 40% more than Southern Pine.
Three estimates we had to make, flagged where they appear:
- Polycarbonate glazing. The plans call for 1/4-inch clear UV-protected polycarbonate. We couldn’t read a listed price for that sheet, so we estimated $350 per 4’ x 8’ by scaling a plastics retailer’s listed prices for thinner and smaller sheets (eplastics). We count about 17 sq ft of finished pane per sheet, the yield our Spica greenhouses actually achieved with diamond panes.
- Pier connectors. Each pier takes an uplift-rated post base and post cap. The store listed bases (a 6x6 base at $60.99) but no caps, so we priced each cap at the base’s price. That line is on the high side.
- General fasteners. Sheathing, subfloor and framing screws and nails, priced from a 25-lb box of exterior screws ($121.99) at roughly 80 screws to the pound.
The materials, line by line
Rounded to the nearest $10; columns may not add exactly.
| Line | Mira Zome 16 | Capella Zome 25 | Borealis Zome 40 |
|---|---|---|---|
| Panel frames: 2x6 struts | $420 | $1,090 | $2,310 |
| Skins: 1/2” CDX plywood | $300 | $900 | $2,340 |
| Roofing: underlayment and architectural shingles | $580 | $1,440 | $3,890 |
| Glazing: 1/4” polycarbonate (estimate) | $1,400 | $3,500 | $7,350 |
| Closed-cell foam in the frames and joints | $2,320 | $7,250 | $20,460 |
| Drywall over the foam (the thermal barrier) | $120 | $400 | $1,090 |
| Shell subtotal | $5,130 | $14,580 | $37,440 |
| Pony wall and base plate (lumber, structural sheathing, foam) | $1,780 | $2,810 | $4,670 |
| Floor: 2x10 framing, 3/4” subfloor, batts, underside closure | $950 | $2,230 | $5,510 |
| Piers: concrete | $670 | $810 | $1,080 |
| Piers: post bases and caps (estimate) | $3,420 | $4,150 | $5,490 |
| Entry: door wall, awning, doors, landing or deck, steps | $1,060 | $1,780 | $1,340 |
| Structural screws, straps, hold-downs and other fasteners | $1,600 | $2,710 | $3,610 |
| Panel jigs: plywood or OSB boards and stop blocks | $220 | $400 | $840 |
| All plan materials | $14,830 | $29,480 | $59,990 |
| Per sq ft of floor | $96 | $69 | $54 |
| Shell only, per sq ft of floor | $33 | $34 | $33 |
What’s behind some of the lines:
- The struts are 36 boards for the Mira (12 at 12’ and 24 at 16’), 102 for the Capella (57 and 45) and 237 for the Borealis (191 and 46): 164, 310 and 427 struts.
- The skins are 11, 33 and 86 sheets. The Capella has 24 skins wider than a 4’ x 8’ sheet and the Borealis 89; each goes on in strips over a nailer framed into the panel, so every piece comes from a stock sheet.
- Roofing is 4, 10 and 27 squares, with waste. Hip caps, drip edge and flashing aren’t in this line.
- Glazing is 4, 10 and 21 sheets by our yield estimate, for 67, 156 and 352 sq ft of panes.
- Foam is 1,300, 4,070 and 11,490 board feet in the panel frames and joints, plus 620, 1,000 and 1,590 for the pony wall (in the base line).
- The Mira’s entry includes its 12-foot deck with guards and steps; the Borealis has one entry with a 6-foot door pair, which we priced as two single 36-inch prehung doors because no prehung pair was listed. A real pair costs more. The Capella’s and Borealis’s glazed transom units aren’t priced.
- The jigs aren’t in the plans’ materials lists, but you need them: 8, 15 and 32 sheets of 3/4” board, and five or six 8-foot 2x4s for stop blocks.
Not priced at all: sheathing tape, coil strap, joist hangers, handrails, flashing, caulk, exterior trim and paint. They’re small next to the lines above, but they’re real.
Plan · Home · Cabin or small ADUCapella Zome 25A 430 sq ft zome cabin with 97% standing room.25'-8 5/8"430 sq ftfrom $59
Where the money goes
Three things stand out.
Insulation is the shell. Closed-cell foam is 45 to 55 percent of the shell’s material cost at every size, three to four times what the shell’s lumber and plywood cost. The plans fill each 2x6 frame with closed-cell foam (about R-36), which also seals each skin to its frame. At these volumes, get an installed quote from a spray-foam contractor and compare it with kit prices; we’ve priced only the kits.
Lumber is the small part. The Capella’s 310 struts cost about $1,090. Buying in bulk tiers (50 or more of a size) would cut that by about $160 at this store. Swapping the plywood subfloor for 23/32” T&G OSB ($25.79 a sheet) saves about $410 on the Capella, if your engineer and code allow it.
Size helps. Per square foot of floor, all plan materials fall from $96 on the Mira to $54 on the Borealis, because doors, landings, jigs and connectors don’t grow with the floor. Shell-only cost stays near $33 per square foot at every size, since a zome’s shell grows in step with its floor.
Labor
Our plans are written for owner-builders, so labor is often your own. If you hire it, two numbers help.
- Wages. The median pay for carpenters was $29.12 per hour in May 2025 (US Bureau of Labor Statistics). That’s a wage; a contractor’s billed rate also carries payroll costs, insurance, overhead and profit.
- Work content. We haven’t published timed builds yet; the build diaries will report measured hours. Until then, count the work. The Capella is 82 panels, 310 struts in 21 distinct saw setups, 930 screws in the panel corners and 628 more joining panels, 33 skins and 10 squares of roofing. The Borealis is 111 panels and 427 struts.
A practical way to estimate your own labor: build one jig and one panel of each shape before you buy everything, time it, and multiply by the panel counts. As an illustration only, if a two-person crew averaged one hour per panel including cutting, the Capella’s panels would take 82 crew-hours, about 164 person-hours, or about $4,800 in wages at the median rate. Raising, skinning, roofing, foam, the floor, the pony wall and the doors all come on top.
Zomes do have a labor advantage over geodesic domes: at 30 feet our zome has 82 panels against 352 for the dome. See Zome vs geodesic dome.
What the plans don’t cover, and what it costs
Our plans cover the shell: frame, skin and glazing, base, piers or footing, structural floor, doors, windows and the outside steps and landings. Plumbing, wiring, heating, kitchens, bathrooms, interior walls, flooring and finishes are left to the builder. For a home, that’s most of the budget.
The best public benchmark is NAHB’s Cost of Constructing a Home survey for 2024: an average construction cost of $428,215 for a 2,647 sq ft new home, or about $162 per square foot, excluding the lot, the builder’s overhead and profit. Its breakdown lets us price the parts our plans leave out at contractor rates:
| NAHB category (2024) | Share of construction cost | Per sq ft of finished floor |
|---|---|---|
| Major systems rough-ins (plumbing, electrical, HVAC) | 19.2% | $31.10 |
| Interior finishes, less insulation and drywall | 19.2% | $31.14 |
| Site work (permit and impact fees, utility fees, engineering) | 7.6% | $12.36 |
| Final steps (landscaping, driveway, outdoor structures, cleanup) | 6.5% | $10.47 |
| Other | 2.1% | $3.34 |
| Not covered by our plans | 54.6% | about $88 |
| Foundations, framing and exterior finishes (the shell’s share) | 40.5% | $65.45 |
| Insulation and drywall (in our plan materials) | 4.9% | $7.92 |
Applying about $88 per square foot to our three zomes gives a finish allowance of about $13,700 for the Mira, $38,000 for the Capella and $99,000 for the Borealis. Treat it as a planning number. Small buildings cost more per square foot, because a kitchen, a bathroom, a water heater and a permit don’t shrink with the floor; a glamping pod with no kitchen or bath may need much less than this.
Turnkey: what a contractor-built zome costs
Nobody publishes measured turnkey costs for timber zome homes, so here’s a bracket built from the pieces above.
- Plan materials (from our table) plus the finish allowance (NAHB rates) gives what an owner-builder who frames the shell and hires the trades might spend.
- A contractor’s margin. In NAHB’s survey, construction cost is 64.4% of the sale price, overhead 5.7% and profit 11.0%. Adding overhead and profit to cost multiplies it by about 1.26.
- Shell labor, which we can’t yet price from measurements.
| Mira Zome 16 | Capella Zome 25 | Borealis Zome 40 | |
|---|---|---|---|
| Plan materials | $14,800 | $29,500 | $60,000 |
| Finish allowance at NAHB rates | $13,700 | $38,000 | $99,000 |
| Owner-builder with hired trades | $28,500 ($184/sq ft) | $67,500 ($157/sq ft) | $159,000 ($142/sq ft) |
| With contractor overhead and profit, before shell labor | $35,900 ($232/sq ft) | $85,000 ($198/sq ft) | $200,200 ($179/sq ft) |
Two cross-checks. NAHB’s average home works out to about $204 per square foot once overhead and profit are added to its $162 cost, and a contractor-built Capella lands near that before anyone is paid to frame the shell. Cost-guide publishers put finished dome homes of all kinds, concrete and timber together, at roughly $100 to $250 per square foot (HomeAdvisor, a cost-guide figure). Both suggest a contractor-built zome home is a $200-plus-per-square-foot project once the shell labor is in, and more for a small one.
None of this includes land, excavation and footings below the piers, a well, septic or a long utility run, delivery, sales tax, tools, scaffolding or financing.
Summary
| Mira Zome 16 | Capella Zome 25 | Borealis Zome 40 | |
|---|---|---|---|
| Floor inside the pony wall | 155 sq ft | 430 sq ft | 1,120 sq ft |
| Shell materials | $5,130 | $14,580 | $37,440 |
| All plan materials (DIY) | $14,830 | $29,480 | $59,990 |
| Owner-builder with hired trades | about $28,500 | about $67,500 | about $159,000 |
| Contractor-built, before shell labor | about $35,900 | about $85,000 | about $200,200 |
How to use this: start from the plan-materials line, replace our prices with your yard’s, swap the estimates (glazing, connectors, foam) for real quotes, then decide which of the finish work you’ll do yourself. For geodesic domes priced the same way, see How much does a dome home cost?; for the permit side, Dome and zome permits.
Plan · Home · Permanent homeBorealis Zome 40The flagship: a 40-foot zome home under a glass star.40'-3 7/8"1,121 sq ftfrom $59
Sources
- Our plans’ build guides and materials lists: Mira Zome 16, Capella Zome 25 and Borealis Zome 40 (2x6 editions).
- McCoy’s Building Supply, web catalog, San Marcos, Texas store, prices read 2026-11-15.
- eplastics, clear polycarbonate sheet, listed prices used to estimate 1/4-inch sheets.
- Trading Economics, Lumber futures, read 2026-11-15.
- NAHB Economics, Cost of Constructing a Home, 2024 (January 2025), and the summary on Eye on Housing.
- US Bureau of Labor Statistics, Occupational Outlook Handbook: Carpenters.
- HomeAdvisor, dome home cost guide, cost-guide figures.
Questions
Q01How much does a zome cost to build?
For the materials in our plans (shell, base wall, floor on piers, entry, fasteners and jigs) we priced about $14,800 for a 16-foot pod, $29,500 for a 25-foot cabin and $60,000 for a 40-foot home, at one building-supply chain's prices on 2026-11-15. A finished home costs much more once plumbing, wiring, heating, interiors and labor are added.
Q02What is the most expensive part of a zome shell?
Insulation. In our plans the frames are filled with closed-cell spray foam, and at DIY kit prices that is 45 to 55% of the shell's material cost, three to four times what the shell's lumber and plywood cost. Glazing is second.
Q03Is a zome cheaper than a geodesic dome?
Not in materials. Our hemispherical domes cover each square foot of floor with less shell, so their shell materials cost 8 to 15% less per square foot of floor. Zomes have far fewer panels and struts, which can save labor.
Q04What does a turnkey zome home cost?
Nobody publishes measured turnkey costs for timber zomes. Using national construction-cost survey rates for everything our plans don't cover, a contractor-built 430 sq ft zome cabin comes to about $85,000 before anyone is paid to frame the shell, or roughly $200 per square foot and up.
Q05Does the cost include the foundation?
Our materials figures include the floor framing, subfloor, concrete for the piers and the piers' connectors. They do not include excavation, footings below the piers, site work, utility connections, permits, engineering, delivery or sales tax.